California permit guide

Build a complete California ADU permit packet.

Use the state's review clock correctly, give every agency the same property facts, and assign each permit task before drawings start.

Request a local builder shortlist

We manually compare your city, ADU type, project stage, and budget with builder-published local-service evidence, ADU focus, and a dated check of the current CSLB record. We follow up by email after review.

A completed detached accessory dwelling unit with a wood exterior and large windows
A preapproved design is not a permit for your lot. The site, utilities, foundation, and local conditions still need review.

First decision

Your permitting agency

Completeness notice

15 business days*

Complete application

60-day decision*

Before occupancy

Final approval required

*California's statutory clocks apply to the agency's completeness determination and decision on a completed application. They are not a promise for design, corrections, permit issuance, construction, or inspections.

The permit clock

Completeness, approval, issuance, and occupancy are four different gates.

California's March 2026 ADU Handbook says a permitting agency must tell you whether an ADU application is complete within 15 business days. If it is incomplete, the written notice must identify the missing items and explain how to complete the application.

Once the application is complete, the agency generally has 60 days to approve or deny it when an existing primary dwelling is already on the lot. That does not mean a permit will be in hand 60 days after you first call a designer. Property research, drawings, agency corrections, fee payment, and project-specific reviews sit before or around that clock.

Read California HCD's March 2026 ADU Handbook
  1. 01 · Jurisdiction

    Find the agency

    A mailing address can sit outside city limits. Confirm whether the city, county, or another agency issues the permit.

  2. 02 · Feasibility

    Screen the property

    Check legal structures, lot constraints, access, utilities, easements, trees, fire conditions, and any coastal or historic review.

  3. 03 · Drawings

    Build one coordinated set

    Align the site plan, architecture, structure, energy documents, and utility assumptions before intake.

  4. 04 · Intake

    Earn completeness

    Submit every required form, plan, calculation, and agency document in the current local format.

  5. 05 · Review

    Close corrections

    Keep one response log so comments from planning, building, fire, and utilities do not conflict or disappear.

  6. 06 · Closeout

    Issue, build, inspect

    Pay the current fees, pull permits, schedule required inspections, and obtain final approval before occupancy.

Permit packet

Start with eight coordinated parts, then use your agency's checklist.

California does not use one universal ADU application packet. Local staff review the application, site plan, building plans, and other documents against objective standards. Ask for the current checklist before paying for a complete drawing set.

The list below is a coordination tool, not a substitute for your city or county's forms.

01

Application and project contacts

Owner, applicant, designer, contractor when known, project address, scope, valuation, and declarations.

02

Property and zoning facts

Parcel boundaries, existing legal structures, use, lot coverage, easements, setbacks, overlays, and recorded constraints.

03

Scaled site plan

Existing and proposed buildings, dimensions, setbacks, access, parking when applicable, grading, drainage, and utility routes.

04

Architectural drawings

Floor plans, roof plan, exterior elevations, building sections, room uses, doors, windows, and life-safety information.

05

Structure and foundation

Structural plans, details, calculations, foundation design, and existing-condition verification for conversions.

06

Energy documents

The applicable California Energy Code compliance package for a detached new build, addition, or alteration.

07

Utility plan

Electrical load and service, water, sewer or septic, gas if used, meters, trenching, and agency approvals.

08

Site-specific studies

Fire access, grading, soils, protected trees, flood, coastal, historic, or other documents only when the property triggers them.

Project type changes the packet

Existing permitted space

Garage or interior conversion

Prove what was legally built, then document how the existing structure, fire separation, ceiling height, light, ventilation, access, and utilities will support a dwelling.

Main risk: hidden or unpermitted existing conditions.

New building

Detached ADU

Coordinate a full foundation, building envelope, structure, energy package, drainage, utility connections, site access, and any required solar or battery-ready provisions.

Main risk: site and utility scope left out of the design proposal.

Repeatable building design

Preapproved plan

Reuse the approved building-design set, then add the property-specific title sheet, site plan, foundation, drainage, utility, access, and local application documents.

Main risk: treating plan approval as site approval.

Energy treatment also changes by project type. The California Energy Commission treats a new detached ADU as new construction, attached ADUs and conversions of unconditioned space as additions, and conversions of conditioned space as alterations.

Fees and utility charges

There is no dependable statewide permit price.

Ask your agency for a written estimate that separates plan review, permit issuance, impact fees, school fees, utility review, connection or capacity charges, and any property-specific review.

Impact fees

An ADU with 750 square feet or less of interior livable space is exempt from impact fees. Larger ADUs may be charged proportionately under state law.

Permit and plan review

The impact-fee exemption does not erase plan review, building permit, or project-specific agency charges. Current local schedules control.

Water and sewer

Existing-space ADUs and JADUs receive specific protection from being treated as a new residential use for connection-fee calculations, with exceptions and proportionality rules. Get the utility's determination in writing.

School fees

School districts may levy impact fees on ADUs larger than 500 square feet. Confirm whether the district charges them before finalizing the budget.

Responsibility map

Most delay starts in the handoff between people.

Before signing, put one name next to every permit task. A design agreement that stops at drawings and a construction agreement that starts after permits can leave no one responsible for intake, corrections, or agency coordination.

Task Name the owner Evidence to request
Property research Owner, designer, or feasibility consultant Written zoning, permit-record, easement, overlay, and utility assumptions
Permit drawings Designer plus required engineers Sheet list, included calculations, exclusions, and revision rounds
Agency intake Named applicant or permit coordinator Submission receipt, completeness notice, fee invoice, and permit number
Corrections Designer, engineer, builder, and utility contacts by topic Comment log, response letter, revised-sheet index, and resubmittal date
Inspections and closeout Builder and owner Inspection record, approved changes, finals, and certificate of occupancy

Choose the project team

Compare permit scope before comparing price.

Give every bidder the same property facts, intended unit type, utility assumptions, and finish level. Then compare what each proposal includes for drawings, engineering, fees, corrections, construction, inspections, and closeout.

  1. 01

    Verify the contractor license

    Check the current CSLB record, classification, bond, workers' compensation information, and available complaint disclosure.

  2. 02

    Call recent local references

    Ask what changed during plan review, who answered corrections, how utilities were handled, and whether final inspection closed cleanly.

  3. 03

    Compare exclusions and allowances

    A lower proposal may simply omit permit coordination, utility work, site conditions, fees, finishes, or correction rounds.

Local permit starting points

Permit FAQ

Five answers to use before you buy plans.

Do you need a building permit for an ADU in California?

Yes. An ADU is a dwelling unit, so the project needs approval from the local permitting agency before construction and a certificate of occupancy before anyone moves in. The exact forms and reviews depend on the property, project type, and local agency.

How long does a California ADU permit take?

The permitting agency must generally determine whether an ADU application is complete within 15 business days and approve or deny a completed application within 60 days. Feasibility, design, corrections, permit issuance, construction, inspections, and special reviews can make the full project much longer.

What plans do I need for an ADU permit?

A typical package includes an application, site plan, floor plans, elevations, sections, structural information, energy documents, and utility details. Your city or county sets the exact checklist and may require additional documents for grading, fire access, trees, historic resources, septic systems, or coastal review.

Are California ADUs exempt from permit fees?

Not from every fee. State law exempts an ADU with 750 square feet or less of interior livable space from impact fees, but plan review, building permit, utility, school, and project-specific charges may still apply. Ask the permitting agency for a written fee estimate for your exact scope.

Does a preapproved ADU plan skip the permit process?

No. A preapproved plan can reduce review of the repeatable building design, but the local agency still reviews the property-specific site plan, zoning, foundation, drainage, utilities, access, and other applicable conditions before issuing a permit.

Your next step

Turn the permit checklist into one project brief.

When suitable builders are available, your shortlist may include up to three evidence-backed matches. We manually compare your city, ADU type, project stage, and budget with builder-published local-service evidence, ADU focus, and a dated check of the current CSLB record. We follow up by email after review. We share your brief only with your consent. A request does not guarantee a match, a specific match count, a builder response, response time, price, or project outcome.

Official resources

State law, building codes, energy requirements, fees, and local procedures change. Confirm the current rules for your property with the permitting agency before relying on a schedule, design, or budget.